ATLANTA 12/6/17: Public interest groups and private citizens will converge on the Georgia Public Service Commission in December to confront Georgia Power about its Vogtle 3 & 4 construction fiasco at the 17th Semi-Annual Vogtle Construction Monitoring Review (VCMR). These reviews have occurred roughly every six months since construction commenced on Vogtle 3 & 4 reactors in Burke County in 2010, but this is the first time that Commissioners have officially asked the question whether to cancel the troubled project which is at least five years behind schedule and has doubled in price to $25 billion. The only other reactors under construction in the . were cancelled by South Carolina utilities on July 31, 2017, following the bankruptcy of Westinghouse in March.